Thursday, 20 October 2011

Blockwork completed



All the blockwork has now been completed and the external bricks have been delivered.

Pitches between 49 and 64



The hardcore is now being laid for the new road between 49 - 64

Digging out the road




Digging out the road between pitches 49 - 64

Blocks and Builders



Upward view of the new toilet block and a view of the new developement for pitches 49 - 64

The footings for the Toilet Block

Progress!! most of the blockwork on the foundations has now been completed

New road between pitches 49 & 64



The new road is now being created in-between these pitches

Blocks and Builders



The base is going up!