Wednesday, 1 February 2012

Turfing on pitch 49



Turfing has begun on pitches 49 - 55

Carpenters



Thank you to K.P Rich Construction and IW Smith Carpentry with their assistance with the roof of the new toilet block.

Tiling the roof



One side of the roof has now been completed. Kevin is working really hard to try and complete it before the bad weather sets in!

Delivery of Roller and Dumper



Delivery onsite of the roller and dumper for the roads and the pipes for the entrance,. We are going to pipe part of the stream at the entrance to aid easier access into the site.

Tiling the roof



The roof is now being tiled

pitches 49 - 55



New superpitches are now taking shape

Roof cladding



Wider view of the roof