Monday, 27 February 2012

Swapped 9 old caravans with 9 new ones!



Its taken the whole weekend but we have mananged to swap over 18 caravans!! Now the old ones are being parked on the campsite ready to be moved off site as we open in 16 days time!! (so no pressure then!! )

Island Crane



Thanks to Island Crane hire for all their expertise and help

All the old caravans have now been pulled off



All we have to do now is site all the 9 new ones!!

spinning her round



The caravans have to be turned mid air as we have to pull them on backwards

New caravan



Weather picked up on Sunday it was a lovely day for hauling caravans in the air!!

Here she comes!!



Getting ready to pull the New Tennyson onto site

Taking a well earned coffee break



Thanks to the gang ! Nick, Hugh, Dave, Vince and Island Cranes. We couldn't have managed without you! Thank you very much :-)

Old ones out!!



Getting ready to set the caravan up for its exit

Off we go!!!



Ready for take off!!

Big gaps!!



The caravans are rapidly disappearing!!!

Caravans are everywhere!!

You can't see the carpark for caravans!!

Crane preparing for lift off!!!



The crane is getting ready to lift the old vans off site

More waiting to come off!



Two Stenbury caravans waiting to come off

Old caravans queueing up!!




The old vans are queueing up to come off!

Carpark full up!!



No room for cars!!!


Crane is getting ready to lift!!

Ready and waiting!!

Big weekend! We have 9 caravans to take off and 9 caravans to lift on!! So its a major weekend ahead!


All the new caravans have now been pulled onto the carapark so that they can be lifted over the wall

Last Tennyson to arrive



Finally the last Tennyson caravan has arrived so we can now begin to pull the old vans off and then replace with the lovely new ones!!

Thursday, 9 February 2012

Pitches 56 - 62

Remember this was what the pitches between 56 - 62 used to look like!! (sloping!! )

What an improvement!

Many thanks to Dad for his vision to make this area more usable!

As these pitches could only really be used for tents as when touring caravans went on these pitches we had to chock them up on the far side to make them level! Not any more!!

Turfing on pitch 56




Many thanks to Elliott from Hillcroft Turf who has worked really hard in adverse weather condtions (-2 degrees) some days!

He has made an amazing job of the turf it looks like a bowling green!!

Pitches 56 - 62



A closer view of these pitches from 56 - 62 as you can see the gabion baskets break up this area making it a focal point for the middle of the field.

Pitches 56 - 62 will only be used for motorhomes and campervans.


Pitches 49 - 55 will be used by Touring caravans and Motorhomes.


You can see in the background the new Tennyson caravans temporarily using the field as a 'car park'!

Pitches 56 - 62



This row has now been completed and looks really nice. The gabion baskets compilment this area and it helps to break up the field to provide interest.

Grass bank below pitch 56



The bank below 56 - 62 has also been turfed to finish off this section and it looks really nice

pitch 56



This is the last pitch left to be turfed in the new middle section of the field. This row between 56 - 62 will only be used for Motorhomes.

New Tennyson caravans



This an external shot of the new Tennyson static caravans. They have been temporarily parked on the camping field as we have accumilated a build up of static caravans in the main car-park !! So the camping field is currently being used as a ''temporary carpark'' for static caravans!!

Once the weather gets alittle warmer they will be re-located into the Orchard.

Internal door of the toilet block




The external and internal doors have been handcrafted on the island by 'The Joinery Shop' They have made a beautiful job. Thank you very much!


The doors have been made out of a hardwood called Terminalia Ivorensis ( idigbo for short )!

(don't worry I can't say it either!! )


The entrance to the building looks really impressive now as the design of the doors makes it a real feature in itself. The wood has been preserved with natural oils to bring out the varing shades and hues.

Ladies new toilet block



A wider view of the ladies in the new toilet block.

All the partitions have now been built and the second fix has begun. The tiler will continue working around the base line and then we are having mosaic tiles to break up the vastness of white tiles otherwise it will be boring just to look at a blank wall!

Wednesday, 8 February 2012

Ladies new toilet block



The internal walls have now been built and the tiles are now being fixed to the wall

Gents new toilet block



We have now built the internal walls and the plumbers and electricians have carried out the first fixing.

Wednesday, 1 February 2012

Delivery of the Tennyson static caravan



It is now ready to be off loaded

Delivery of the Tennyson static caravan



Finally its in the drive!

Delivery of the Tennyson static caravan



easy does it!

there are only inches to spare!

Delivery of the Tennyson static caravan



Thanks to the Wight Caravan delivery team it is expertly manoeuvered into the site.

Delivery of the Tennyson static caravan





The caravan is 12ft x 35ft and does not bend in the middle!! so it requires skill and patience to manouvre them onto site.

Delivery of the Tennyson static caravan



The caravan is 12 foot wide and there are only inches to spare on both sides!

Delivery of the Tennyson static caravan



The road is getting narrower!

New Tennyson caravans



We now have had the delivery of the new Tennyson static caravans. This is the first image of the caravan coming down Appuldurcombe Road

pitches 49 - 55



A wider view of pitched 49 - 55

Laying of Turf



Laying of turf on pitch 54



pitches 49 - 55



Pitch 49 is the first pitch in this new row of superpitches

Pitches 56 - 62



The ground is being prepared for the turf

pitches 49 - 55



The turf has now been laid

New road and turf



The ground has now been prepared and the turf can now be laid

Preparing pitches 56 - 62 for turf



Another view of these pitches

Turfing on pitches



More work needed to prepare the ground before the turf can be laid

New road between pitches 56 & 62



The new road has now been laid next is the turf!

Turfing on pitch 49



Turfing has begun on pitches 49 - 55

Carpenters



Thank you to K.P Rich Construction and IW Smith Carpentry with their assistance with the roof of the new toilet block.

Tiling the roof



One side of the roof has now been completed. Kevin is working really hard to try and complete it before the bad weather sets in!

Delivery of Roller and Dumper



Delivery onsite of the roller and dumper for the roads and the pipes for the entrance,. We are going to pipe part of the stream at the entrance to aid easier access into the site.

Tiling the roof



The roof is now being tiled