Wednesday, 21 December 2011
Gabion Baskets pitches 57 - 63
After a months work the baskets have now all been filled and hardcore has been laid on the roadway
Roof Membrane
The roof membrane is nearly completed only the top section is left to cover in
Roof Progress
The roof trusses and timber stucture has now been completed and the breathable membrane is now being applied so that it is water tight!
The roof now needs to have the infill of timber
Ground view of the new block
Work begins on the roof
The main roof trusses have now been assembled and the roof is beginning to take shape
Ready for the roof
All ready for the roof now!
Many thanks to Builders R.A.Daish and Sons for their hard work in building the foundations of the new block.
Front of toilet block
Finishing off the front of the block
External walls toilet block
The external brick walls have now been completed
The roof trusses have arrived
The roof trusses have arrived!
Thursday, 1 December 2011
Fencing between pitches 57 - 64
A wider view of the fencing along the edge of the lower pitches. More stone has been delivered for the Gabian baskets
New Toilet Block Development
This are is going to be the ladies!!!
New Toilet Block Development
This is going to be the gents!
New Toilet Block Development
This is the front view of the toilet block
New Toilet Block Development
This is the side view where the wash up area will be located
Back of the toilet block
The builders are really doing a really good job and it is taking shape!
External walls toilet block
The external brick walls are now taking shape
Gabian Baskets
All the baskets have now been assembled, all we have to do now is fill them!!
Fencing between pitches 57 - 64
The new fencing has now been completed on this section. This area is now ready to be levelled again and the hard core bedded down.
Re-location of caravan
Brighstone no: 22 has now been re-located to plot 32 so that all the lower caravans are now the same model. All we need to do now is level it up
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
https://twitter.com/Appuldurcombe
Followers
Blog Archive
►
2013
(1)
►
March
(1)
►
2012
(127)
►
October
(10)
►
July
(45)
►
May
(6)
►
April
(12)
►
March
(2)
►
February
(52)
▼
2011
(153)
▼
December
(20)
Gabion Baskets pitches 57 - 63
Roof Membrane
Roof Progress
The roof now needs to have the infill of timber
Work begins on the roof
Ready for the roof
Many thanks to Builders R.A.Daish and Sons for th...
Front of toilet block
External walls toilet block
The roof trusses have arrived
Fencing between pitches 57 - 64
New Toilet Block Development
New Toilet Block Development
New Toilet Block Development
New Toilet Block Development
Back of the toilet block
External walls toilet block
Gabian Baskets
Fencing between pitches 57 - 64
Re-location of caravan
►
November
(27)
►
October
(55)
►
April
(7)
►
March
(34)
►
January
(10)
►
2010
(44)
►
November
(17)
►
May
(13)
►
April
(1)
►
March
(3)
►
February
(3)
►
January
(7)
About Me
Appuldurcombe Gardens
View my complete profile