Tuesday, 22 November 2011

New Toilet Block Development



An alternative view of the new toilet block developement.

New Toilet Block Development



A wider view of the new toilet block development

Wild rabbit (you wouldn't think so!! )



I had to share this with you! Would you believe it! This is a wild rabbit! It was sunbathing by the wall the other day and was enjoying itself so much it completely ignored me, and carried on sunbathing in the exceptionally warm November sunshine!

Caravan no: 32



An empty space where caravan no: 32 used to be. We will shortly re-locate no:22 to this spot so that all the lower caravans will then match.

Gabian Baskets



The fencing is now being incorporated into the baskets

Chestnut Fencing




This has all got to be made into a fence!

Gabian Baskets



Two of the baskets have now been completed

Chestnut Fencing



There's alot of fencing!! We are going to be busy!

Chestnut Fencing



Now we have to make sence of the heap of fencing

Gabian Baskets



A few baskets have now been setup ready for the hardcore and stone

New Toilet Block Development



The inner wall has now been completed. The outer wall will be partial bricks and then boarding.

Caravan no: 32



slowly does its onto the carpark!

Caravan no: 32

It has now been lifted over the wall and is being guided into the carpark

Caravan no: 32



Off it goes!!!!!!!!

Caravan no: 32



It is being craned over the wall

Limertone Caravan no: 32



Limerstone caravan no: 32 has now been taken off site. Number 22 which is a Brighstone is being re-located to this spot so that all the caravans in this area will then be all the same.

New Toilet Block Development



The internal walls are now taking shape

Chestnut Fencing



Easiest way to get it off the lorry!!

Chestnut Fencing

The Chestnut fencing has now arrived and will be placed in the gabian baskets along the new superpitches between 49 & 56

Block work



The block work has now been started on the exterior walls of the new toilet block

The Gabian baskets

A few have now been made up and fixed together. Now comes the hard job of filling them and fronting the baskets with a dry stone wall.


The Gabian baskets have arrived



They come in a flat pack format. We now have to make them up.

Cement Base



The cement base has now been laid and it has set. The blockwork can now begin

Foundation membrane



The foundation membrane has now been laid in prepartion for the cement

Monday, 14 November 2011

New super pitches 49 - 64

The pitches are taking shape and the gabion baskets have now arrived. These will be used to secure the top bank and will create a natural drainage.

New pitches 49 - 56



These pitches have now settled down and we have sown the grass seed

Pitches 57 - 64



The hard core on the new pitches is now bedding down and we will be able to sow the grass seed.